BAHRAIN MANUFACTURING SITE

Manufacturing

A power quality issue, where a local contractor had recommended a very costly solution.

The problem in detail


Our clients’ engineers were aware of a power quality issue at the company’s Bahrain site where a local contractor had recommended a costly installation of detuned capacitor banks and active filters.

Finding the solution

Using measured harmonic figures, our power systems engineers modelled the system and recommended a more cost-effective solution of passive 5th harmonic filters.

Making it all work

We manufactured, installed and commissioned four 5th Harmonic Filters. An initial filter was commissioned in 2017 to prove the solution and a further three filters were installed in 2018.

What that means for the project now:

We delivered a much more cost effective solution to the site to give effective harmonic filtering giving a total of 1.4MVAr connected at 415V.

check

Everything is Documented

check

Deliveries can be Heavy

check

Hot work!

check

Measurement is Critical

check

Everything is Documented